Construction works of traffic interchange on the 57th km of highway M-5 «Ural» are in progress.

The preparatory works on arrangement of rotational camp equipped with all necessary communication means and computer equipment were completed in April, the temporary field roads are built and field water drain is provided.

IMG_291The major scope of works is completed on disafforestation, stripping of vegetation, the works on filling of body are in progress simultaneously on several segments of interchange.

26 road-building machines and about 50 vehicles are involved in works on site.

 

 

 

 

 

 

 

 

 

Photographic materials on works progress are given in section "Our projects".