Laying of the underlayer at «Formula-1» facility.

In September 2011 "Autoban" Russian-German Joint Venture, LLC, has started the laying of the underlayer (binder) at the "Formula-1" facility.

Read more: Laying of the underlayer at «Formula-1» facility.


Performance of works for the Formula-1 Project

The work package for installation of C-5 macadam-sand mixture and the top roadbed layer of a porous coarse-grained road concrete mix is continued on the main path and cut-offs of the race track.

Read more: Performance of works for the Formula-1 Project


Implementation of the GPS monitoring system for motor transport and road building machinery is continued.

Autobahn has a system of GPS monitoring of motor transport and road building machinery implemented. The system allows to track movement of machinery in real time, and also to perform control over fuel consumption. Introduction of the system allowed to save over 1 million rubles during the first half-year of 2011.

Fuel control sensors and navigation systems were installed on 24 units of machinery starting from the end of June and throughout July.


Opening of the bypass road

The temporary bypass road was opened for traffic on August 23, 2011.

Read more: Opening of the bypass road


Works for construction of a traffic interchange on the 57th km of M-5 “Urals” motorway are continued.

Works for construction of the road dressing, roadbed fill-slope protection and installation of drainage facilities are currently being performed at the traffic interchange. The works for land filling of the cones of the overhead crossing are complete, and asphalt concrete pavement will be constructed upon it in the nearest future. Construction of a temporary bypass road will be completed in the first half of August with traffic switched to that road, which allows us to complete the work package on the Moscow Small Ring Road on the side of Bronnitsy