Latest news

Новости


Construction of a traffic interchange on the 57th km of M-5 “Urals” motorway

The final phase of the land filling operations for the earth roadbed was started in June (some 85% of the overall amount was filled). Works for construction of the macadam base and lower layers of the asphalt-concrete pavement are continued. Works for land filling of the cones of the overhead crossing, installation of curb stones, drainage facilities, covering of roadbed fill-slopes with vegetable soil and installation of illumination poles were started.

Read more: Construction of a traffic interchange on the 57th km of M-5 “Urals” motorway


Performance of works for the Formula-1 Project

Works for installation of delivery infrastructure networks are currently drawing towards completion on the territory of the race track.

 

Read more: Performance of works for the Formula-1 Project


Works on «Formula-1» site

Presently the works on arrangement of storm water and sanitary sewerage in the territory of motor racing track are nearing completion, as well as the works on roadbed filling and arrangement of sand bedding course.

Read more: Works on «Formula-1» site


The work speed of construction of traffic interchange on the 57th km of highway M-5 «Ural» significantly increased.

In May major works were performed on roadbed filling at the exits of the interchange and at new construction site of М-5 "Ural", the works on arrangement of sand bedding course and macadam base commenced. In the nearest time it is planned to start works on laying of asphaltic concrete, installation of edge trays and curb stones.

Read more: The work speed of construction of traffic interchange on the 57th km of highway M-5 «Ural»...


Construction works of traffic interchange on the 57th km of highway M-5 «Ural» are in progress.

The preparatory works on arrangement of rotational camp equipped with all necessary communication means and computer equipment were completed in April, the temporary field roads are built and field water drain is provided.

Read more: Construction works of traffic interchange on the 57th km of highway M-5 «Ural» are in progress.